MAHARASHTRA KRISHNA VALLEY DEVELOPMENT CORPORATION, PUNE.
Sangli Irrigation Circle, Sangli.
Tembhu Lift Irrigation Project, Tal. Karad, Dist. Satara.
Introduction:
Tembhu Lift irrigation Scheme has been proposed to irrigate the drought prone area from RL 650 m to 855 m i.e. above the command area of Takari Lift Irrigation Scheme. The project is administratively approved in 1996 for Rs. 1416.59 Crores. The scheme envisages lifting of 22 TMC water from Krishna river to Irrigate 80472 Ha. of lands from, Karad, Kadegaon, Tasgaon, Khanapur, Atpadi, Kavathe Mahankal, Sangola Talukas of Satara, Sangli & Solapur Districts. The water requirement is met with from Koyna, Wang and Tarali storage dams. The revised administrative approved cost is Rs. 2106.09 cores which includes Rs. 1750 crores for work portion. The upto date expenditure on the project is about Rs. 842 crores (work portion.)
The scheme consists of constructing Barrage across Krishna river at village Tembhu, Tal. Karad, Dist. Satara & Pump House sat various stages Rising main, Tunnels & canal, distributory network and the water is lifted in five stages at different location.
Salient Features:
Total Command Area : 80472 Ha.
Discharge : 57.3 Cumecs
Total No. of Pumps : 111 Nos.
Power required : 153 MW
Total Length of canal : 409 Km.
Position of works:
The Project work were started in 1996. The head work & canal of all five stages were started simultaneously so as to complete the work before May 2000 in order to utilize water as per Krishna Water Dispute Tribunal Award. The present status of the project is given below.
Economic Viability of running Tembhu Lift Irrigation Project
Details of running and maintenance charges –
Electricity charges
1(A) 1(B)II, III 1(A) & 1(B)-IV, V for 79600 hectares. = 437.29 Million Units
HP calculations
HP calculations for Stage 1(A) to Stage-V- = 217455 H.P.
Total H.P. = 217455 H.P.
K.V.A. calculations
K.V.A. calculations Stage 1(A) to Stage-V- = 142162 KVA
Total KVA = 142162 KVA
Total charges
Fixed charges at Rs. 25/ month / KVA as per HTP – 7
Demand charges 142162 x 12 x 25 = Rs.42648600
Tariff Rs. 1.30 Average rates / unit as per HTP – 7
437.29 Mus. x 1.30
= Rs.568477000
Add 2% penalty charges = Rs.11369540
Total charges
= Rs.622495140
Electricity charges per hectare = Rs.622495140 = Rs.7820/ ha./year-
79600
Irrigation charges as per MKVDC circular = Rs.2340/ha./year
Add 5% for maintenance charges = Rs.508/ha/year
Lift Irrigation charges recoverable for running the Scheme
as per project cropping pattern = (7820 + 2340 + 508 ) = Rs.10668/ha/year
Total maintenance cost = (7820 + 508) = Rs.8328/ha/year
Irrigation charges for 79600 ha. irrigation is
= Rs.10668/ha/year.
No. of rotations in a year = 23 Nos.
Rate of irrigation per rotation = 10668/23
= 463/ha. (Rs.187/acre)
Presently in this area private Lift Irrigation charges are Rs. 500 to Rs. 600/per acre rotation. Therefore, there will not be any difficulty in recovering of Rs.187 / acre, the proposed irrigation charges are recoverable from the beneficiaries. Thus, it can be seen from the above deliberations that the proposed component of Tembhu Lift Irrigation Project is economically viable and should be taken up.
Khanapur Tasgaon 106 Km.
Stage 4 to 5 Feeder canal 7 Kachare wadi 35 Km.
Gorewadi 25 Km.
Total 409 Km.
Present Position of Stage I & II of Tembhu Project, Karad
Sr. No.
Name of Work
Present position of work
1
Tembhu Barrage
Civil work completed 11 gated are installed & 90% Mechanical work completed.
2
Approch channel 1 (A)
Civil work is completed.
3
Pump House 1 (A)
Civil work is completed.
4
Control room 1 (A)
Civil work completed 33 pumps are installed, Other work in progress
5
Pressure filter 1 (A)
40% work completed.
6
Anti surge 1 (A)
Civil work 90% completed.
7
Switch yard 1 (A)
Civil work is completed.
8
Manifold 1 (A)
Civil work 70% completed. Mechanical work in progress work for 1 row is completed.
9
Rising Main 1 (A)
Civil work 90% completed.
10
Railway crossing 1 (A)
Civil work is completed.
11
Pump House Stage 1 (B)
Civil work 90% completed. 6 Nos. of pumps are installed other are in progress.
12
Control room 1 (B)
Civil work is completed.
13
Switch yard 1 (B)
Civil work is completed. Electrical work in progress.
14
Pressure filter 1 (B)
90% work is completed.
15
Anti surge 1 (B)
40% work is completed.
16
Manifold 1 (B)
Work for 1 line is completed and other is in progress.
17
Rising Main 1 (B)
50% work completed.
18
Delevery Chamber 1 (B)
90% work completed.
19
Kambale Tunnel
Work completed 100%
20
Link canal-I Km. No. 1 to 15
80% work is completed.
21
Link canal-II Km. 1 to 23
80% work is completed.
22
Pump House Stage – II
Civil work is completed
23
Control Room II
Civil work is completed
24
Swich Yard – II
Civil work is completed
25
Manifold – II
Work in progress
26
Rising Main – II
90% work is completed
27
Anti Surge – II
40% work is completed
28
Delivery Chamber – II
Civil work is completed
29
Surali canal – II K.M. 1 to 23
80% work is completed
30
Kamathi canal–II K.M. 1 to 15
100% work is completed
31
State Highway Road crossings
Work completed
32
M.D.R./O.D.R. Road crossings
Completed
33
Khanapur – Tasgaon K.M. 11 to 42
K.M. 11 to 20 Earth work completed 21 to 42 work to be done Tender work completed work order issued to agency
34
Khodashi Gated weir
Work is in progress
35
Flood protection wall for Karad Town
Tender process is completed
Sr. No.
Name of Work
Present position of work
1
Tembhu Barrage
Civil work & 90% Mech. work completed.
2
Pump House 1 (A)
Civil work completed. Pumps installed.
3
Rising Main 1 (A) to 1 (B)
90% work completed.
4
Pump House 1 (B)
90% Civil work completed. Pumps installation is in progress
5
Rising Main 1 (B) to Khambale Tunnel
50% work completed.
6
Pump House Stage – II
95% work completed.
7
Rising Main Stage – II
90% work completed.
8
Sural & Kamathi canal
99% work completed.
9
Link canal – I
80% work completed.
10
Link canal – II
80% work completed.
11
Yerala Aqueduct
Work completed.
12
Pump House Stage – III
70% work completed.
13
Rising Main Stage – III
Civil work completed.
14
Devekhindi Tunnel
73% work completed.
15
Stage III A to Ghanand Tank 19 K.M. canal
75% work completed.
16
Ghanad-Hivthad canal – 32 K.M.
75% work completed.
17
Sangola canal 45 K.M.
50% work completed.
18
Kavthe-mahanakal canal 40 K.M.
---
19
Atpadi canal 15 K.M.
---
20
Kahanapur – Tasgaon canal 106 K.M.
5% work completed.
21
Pump House Stage – IV
55% work completed.
22
Rising Main – V
Work completed.
23
Fedder canal stage – IV to V-7 K.M.
68% work completed.
24
Kacharewadi canal – 35 K.M.
---
25
Pump House Stage – V
45% work completed.
26
Rising Main – V
Work completed.
27
Gorewadi canal 25 K.M.
---
3 comments:
Hi Sirji,
First of all thanks much for the detail information.
Here, I would like to know - when can we expect the reimbursement of the land which has acquired for this tembu project.
thnx for statistical info. about project .but there is not mentioned cost of land acquisation for tembhu lift irrigation project and canals and infrastructure . command offices etc. i think most of all bills are paid to contractors for building project, and other infra. but ...but.. we have not received single rupee against our land acquisation for project,how can any govt body pays all other bills except than that of land.i think without any land you cant build any project. when you are going to pay compensation to poor land owners.
We have lost 2.5 acre of land in Tembu Project. I want to know when we get our compensate for our land
Post a Comment